Richmond Signal System - Phase III

Project Summary and Scope

The Richmond Signal System - Phase III project will expand the Richmond Signal System north of the James River in the western, northern, and eastern extents of the City. Approximately 77 signalized intersections operating without communications or with limited wireless communications will be considered for integration into the existing Econolite Centracs© central system software. The project will also provide for the installation of modern traffic signal controllers, some new traffic signal cabinets, communications equipment, and CCTV cameras.

Communications between the central system and each signal cabinet has provided numerous benefits to the City including enhanced remote monitoring, optimized and efficient signal coordination, special events management, and maintenance capabilities, all of which benefit the traveling public.

Part of the Project Written Studies, Reports, Presentation

Project Milestones

Design Phase Completion - by Summer 2019. Procurement Process Completion - by December 2019 Start Project Delivery - by Spring 2020 Project Completion - by Summer 2022

Request for Qualification (RFQ) solicitation posted. Due date 9/20/2019.

Project Funding

Congestion Mitigation and Air Quality Improvement (CMAQ) - $6,312,350 federal funded.

Project Status Updates

5/08/2019 90% design completed.

9/15/2019 design completed.

10/28/2019 request VDOT advertisement authorization.

10/29/2019 RFQ process completed.

12/31/2019 waiting for VDOT advertisementauthorization.

Expenses (costs are reported quarterly)

Expenses - around $900,000

Project Contact Information, if you have questions about this project please contact this individual.

For information about the details of any project first contact the public information office for the department running the project.  For most projects the following people can help:

Performance Measures and Benchmarks

Waiting for Verizon to complete the revison of the Utility Make Ready (UMR) plans.

Waiting for the City-Norfolk Southern agreement execution. - completed

Project Overall Status (Active, Pending or Complete)

Active

Ordinance Information

Ord. No. 2017-211

Contract Information

N/A